You don't have javascript enabled. Good luck with that.
Pencarian
Pembangunan Stasiun LRT Fase 1 Sudah 95 Persen

Stations Construction Hits 95 Percent for LRT Phase 1 Route

Construction progress on Light Rail Transit (LRT) Phase 1 (Velodrome-Kelapa Gading) station has reached 95 percent. There are six stations in this route which are targeted to complete by the end of this year.

Five stations will be completed this November

PT. LRT Jakarta Project Director, Iwan Takwin stated, LRT Phase 1 route is as long as 5.8 kilometers with six stations. Those are Pegangsaan Dua Station located in LRT Depot, Kelapa Gading (North Boulevard) Mall Station, South Boulevard Station, Pulomas Station, Equestrian Station, and Velodrome Station.

End of November, 6 LRT Stations will Be Completed

"Five stations will be completed this November. While the last station in depot will be completed in December," he informed, Monday (11/26).

He is targeting LRT transportation can be operated by the end of January 2019. Thus his side will test to operate this train before it is operated for public.

"Our target is to conduct trial run in two weeks from middle of January. After that it will ready to operate," he mentioned.

Linked News
Popular News indeks
  1. Jakarta Endorses New Housing Project for Residents on Railway Embankments

    access_time28-03-2026 remove_red_eye2402 personDessy Suciati
  2. Pramono Affirms Commitment to Enhancing Regional Financial Management Quality

    access_time02-04-2026 remove_red_eye789 personTiyo Surya Sakti
  3. Pramono Calls for Enhanced Synergy at DPRD Post-Eid Gathering

    access_time30-03-2026 remove_red_eye697 personDessy Suciati
  4. Banners Prohibiting Illegal Parking Levies Installed at Blok M Square

    access_time02-04-2026 remove_red_eye636 personTiyo Surya Sakti
  5. Kampung Rambutan Terminal Sees Increase in Intercity Bus Passengers

    access_time03-04-2026 remove_red_eye504 personNurito