You don't have javascript enabled. Good luck with that.
Pencarian
Pembangunan Stasiun LRT Fase 1 Sudah 95 Persen

Stations Construction Hits 95 Percent for LRT Phase 1 Route

Construction progress on Light Rail Transit (LRT) Phase 1 (Velodrome-Kelapa Gading) station has reached 95 percent. There are six stations in this route which are targeted to complete by the end of this year.

Five stations will be completed this November

PT. LRT Jakarta Project Director, Iwan Takwin stated, LRT Phase 1 route is as long as 5.8 kilometers with six stations. Those are Pegangsaan Dua Station located in LRT Depot, Kelapa Gading (North Boulevard) Mall Station, South Boulevard Station, Pulomas Station, Equestrian Station, and Velodrome Station.

End of November, 6 LRT Stations will Be Completed

"Five stations will be completed this November. While the last station in depot will be completed in December," he informed, Monday (11/26).

He is targeting LRT transportation can be operated by the end of January 2019. Thus his side will test to operate this train before it is operated for public.

"Our target is to conduct trial run in two weeks from middle of January. After that it will ready to operate," he mentioned.

Linked News
Popular News indeks
  1. Rano Reaffirms Jakarta's Vision of Becoming a City of Cinema

    access_time22-10-2026 remove_red_eye5564 personBudhi Firmansyah Surapati
  2. Check Saturday's Traffic Diversions for Jakarta Running Festival

    access_time23-10-2026 remove_red_eye912 personAldi Geri Lumban Tobing
  3. MRT Jakarta Prolongs Weekend Service for Kanye West Concert

    access_time23-10-2026 remove_red_eye815 personAldi Geri Lumban Tobing
  4. MRT Jakarta Modifies Schedule for Jakarta Running Festival

    access_time23-10-2026 remove_red_eye792 personAldi Geri Lumban Tobing
  5. Jakarta–Turkey Film Production to Begin Filming in 2027

    access_time22-10-2026 remove_red_eye737 personBudhi Firmansyah Surapati